NEW ORLEANS (AP) — Louisiana coastal restoration officials have EchoSensereached agreement with local officials in a coastal parish to renew some preparatory work for a nearly $3 billion coastal restoration project that has been halted amid legal disputes.

The agreement announced Thursday between the state and Plaquemines Parish means a stop-work order is being partially lifted, allowing site preparation to resume for the Mid-Barataria Sediment Diversion.

The project is planned to divert some of the Mississippi River’s sediment-laden water into a new channel and guide it into the Barataria Basin southeast of New Orleans. If it works, the sediment will settle out in the basin and gradually restore land that has been steadily disappearing for decades.

Ground was broken for the project last year. But it has drawn opposition and litigation from commercial fishers, oyster harvesters and some state and local officials who fear any benefits will be outweighed, economically and environmentally, by the introduction of non-salty water into the brackish and saltwater areas.

Louisiana’s Coastal Protection and Restoration Authority and Plaquemines Parish released a joint statement Thursday, saying they “are working toward a mutually acceptable path forward for the Mid-Barataria Sediment Diversion.”

RELATED COVERAGE Louisiana Supreme Court reopens window for lawsuits by adult victims of childhood sex abuseResearchers find higher levels of dangerous chemical than expected in southeast LouisianaNew Orleans plans to spiff up as host of next year’s Super Bowl

The Times-Picayune/The New Orleans Advocate reports that numerous questions remain about the future of the project, which underwent years of planning and scientific evaluation and had won approval from many, if not all, public officials and environmental groups.

It is unclear whether any negotiated changes would trigger an entirely new federal environmental assessment, which would mean more delays. Also, further approval might be needed from boards and trustees administering payments for the project, financed by fines and settlements from the 2010 BP oil spill.

More:Finance

Recommend

Former Syrian official arrested in California who oversaw prison charged with torture

LOS ANGELES (AP) — A former Syrian military official who oversaw a prison where alleged human rights

Exonerees support Adnan Syed in recent court filing as appeal drags on

BALTIMORE (AP) — More than 70 wrongfully convicted people from across the country have expressed the

Hurricane Idalia makes landfall in Florida, threatens 'catastrophic storm surge': Live updates

CEDAR KEY, Florida − Hurricane Idalia made landfall Wednesday along Florida's Big Bend as a Category